AGREEMENT
BETWEEN OWNER AND ENGINEER
FOR PROFESSIONAL SERVICES
THIS IS AN AGREEMENT effective as of
City of Bellevue, Idaho
[
]
(“Effective Date”) between
(“Owner”) and
Merrick & Company
(“Engineer”).
Owner’s Project, of which Engineer’s services under this Agreement are a part, is generally identified as follows:
2024 Drinking Water System Improvements
(“Project”).
Other terms used in this Agreement are defined in Article 7.
Engineer’s services under this Agreement are generally identified as follows: The 2023 Drinking Water Facility Plan
identified the following projects for Idaho Department of Environmental Quality compliance:
• SS-1: Seamans Creek New Springs Collection System
• TD-1: Seamans Creek Springs Collection Transmission Reconstruction
• TD-2a: Highway 75 Watermain Improvements – Phase 1
• TD-3: Distribution System Investigation
• LE-1: Seamans Creek Springs Land Purchase and Easements
The overall project will be divided into two components. Component 1 will focus on project TD-2a: Highway 75
Watermain Improvements – Phase 1 to coordinate with the Idaho Transportation Department (ITD) schedule for
design and construction. Component 2 will involve conducting field investigative studies, report preparation,
land survey to support land purchase and easement acquisition, design, and construction services for projects
SS-1: Seamans Creek New Springs Collection System, TD-1: Seamans Creek Springs Collection Transmission
Reconstruction, TD-3: Distribution System Investigation, and LE-1: Seamans Creek Springs Land Purchase and
Easements.
March 24, 2025| | Amy Phelps